A finishes the work in 10 days & B in 8 days individually. If A works for only 6 days then how many days should B work to complete A?s work?
Add to My IQ
 

 | 
Inappropriate
Answer Title
Answer
A does 1/10 of the job every day
B does 1/8 of the job every day
A worked for 6 days, so completion is 6 * 1 /10 = 6/10
B has to do the remaining 4/10

So
x * 1/8 = 4/10
x * 5/40 = 16/40
x = 16/5
=> 3,2 days

Question Tag Title
Tags
None
Question Asked At Title
Asked At
None
Question Job Title
Job Titles
None


Check out our newest job listings!

Post a Job! $49 for 60 days



Your Name:
Add your comment text
 
Related Questions
Related Questions
Flag this interview question as inappropriate Inappropriate
See Answer
If you have done your homework about this organization, now is the time to use that knowledge. Remember, even as a recruited candidate, some facilities will want to understand why you would select them. If you are a recruited candidate, remind them that you were not looking when you were contacted, but that the challenge sounded intriguing and that a solid opportunity for career advancement is important to you.
Create Date
:
Thursday, March 20, 2008
Tags
:
Asked At
:
None
Job Positions
:
Click here to improve the Interview Question, Answer and other fields.
Comments (1) :
1.
tt2tt
Friday, July 04, 2008 10:41 AM
Y so many answers for the same question ?
Flag this interview question as inappropriate Inappropriate
See Answer
Select datediff('2008-09-07','2006-10-02');
Create Date
:
Sunday, May 11, 2008
Tags
:
Asked At
:
None
Job Positions
:
Click here to improve the Interview Question, Answer and other fields.
Comments (0) :
Goto add your comment on the Question 
Flag this interview question as inappropriate Inappropriate
See Answer
10.5 DAYS(11)
Create Date
:
Wednesday, May 14, 2008
Tags
:
Asked At
:
None
Job Positions
:
Click here to improve the Interview Question, Answer and other fields.
Comments (0) :
Goto add your comment on the Question 
Flag this interview question as inappropriate Inappropriate
See Answer
4DAYS.
Create Date
:
Wednesday, May 14, 2008
Tags
:
Asked At
:
None
Job Positions
:
Click here to improve the Interview Question, Answer and other fields.
Comments (0) :
Goto add your comment on the Question 
Flag this interview question as inappropriate Inappropriate
See Answer
7.125
Create Date
:
Wednesday, May 14, 2008
Tags
:
Asked At
:
None
Job Positions
:
Click here to improve the Interview Question, Answer and other fields.
Comments (0) :
Goto add your comment on the Question 
 
• More Related Questions: 
Suggestions & Comments




Share Your Interview Questions
Ask Interview Questions
View Unanswered Questions





Advertise on this site